Part 3 — Pipelines

Determination of Detailed Route and Approval

Section 206

Marginal note:Costs of making representations

 The Commission may, by order, fix an amount that it considers reasonable in respect of the interim or final costs that are incurred by any person who made or will make representations to the Commission at a public hearing under subsection 202(4) and that amount is payable, on an interim or final basis and without delay, to that person by the company whose pipeline route is the subject of the public hearing.