Canadian Energy Regulator Act

S.C. 2019, c. 28, s. 10

In forceCurrent to September 30, 2026 History

Follow

Part 3 — Pipelines

Deviations and Relocations

Section 212

Marginal note:Relocation

  •  (1) The Commission may, by order, on any conditions that it considers appropriate, direct a company to relocate its pipeline if the Commission considers that the relocation is necessary

    • (a) to ensure the safety of persons and the pipeline;

    • (b) to protect the environment;

    • (c) to facilitate the construction, reconstruction or relocation of a highway, a railway or any other work of public interest; or

    • (d) to prevent or remove an interference with a drainage system.

  • Marginal note:Costs of relocation

    (2) The Commission may, by order, direct by whom and to whom the costs of the relocation referred to in subsection (1) must be paid.

  • Marginal note:Procedures

    (3) The Commission must not direct a company to relocate any section or part of its pipeline unless the procedures set out in sections 201 to 205 have been complied with in respect of the section or part to be relocated.

  • Marginal note:Order

    (4) For the purposes of ensuring that the procedures set out in sections 201 to 205 are complied with, the Commission may order the company to carry out the procedures that the company would have been required to carry out if the company had submitted to the Regulator a plan, profile and book of reference under subsection 199(1) and those sections apply, with any modifications that the circumstances require, in respect of any matter related to the carrying out of those procedures.

  • Marginal note:Costs of making representations

    (5) The Commission may, by order,

    • (a) fix an amount that it considers reasonable in respect of the interim or final costs incurred by any person who made or will make representations to the Commission under this section; and

    • (b) direct by whom and to whom the amount is to be paid.

Version in force since August 28, 2019