Skip to content

Canadian Energy Regulator Act

S.C. 2019, c. 28, s. 10

In forceCurrent to September 30, 2026 History

Follow

Part 1 — Canadian Energy Regulator

Section 9

Marginal note:Definition of document of authorization

 In this Part, document of authorization means a certificate issued under Part 3 or 4, a permit issued under Part 4 or 7, an authorization issued under Part 5, a licence issued under Part 7 or an order made under section 214.

Version in force since August 28, 2019