Skip to content

Canada Oil and Gas Operations Act

R.S.C., 1985, c. O-7

In forceCurrent to September 30, 2026 History

Loading…

Part II — Production Arrangements

Interpretation

Marginal note:Definitions

 In this Part,

expert

expert means a person who is appointed under subsection 48.27(2) or an expert panel appointed under subsection 48.27(3); (expert)

perimeter

perimeter means

  • (a) the area in the offshore, as defined in section 48.01, that is within 20 km of the onshore;

  • (b) the area in Nunavut that is within 20 km of the limit of that territory; and

  • (c) the portion of the submarine area — consisting of the areas referred to in paragraphs 3(d) and (e) — that is within 10 nautical miles of the seaward limit of that area; (bande limitrophe)

pooled spacing unit

pooled spacing unit means the area that is subject to a pooling agreement or a pooling order; (unité d’espacement mise en commun)

pooled tract

pooled tract means the portion of a pooled spacing unit defined as a tract in a pooling agreement or a pooling order; (parcelle mise en commun)

pooling agreement

pooling agreement means an agreement to pool the interests of owners in a spacing unit and to provide for the operation or the drilling and operation of a well thereon; (accord de mise en commun)

pooling order

pooling order means an order made under section 31 or as altered pursuant to section 35; (arrêté de mise en commun)

regulator

regulator means a provincial government, a provincial regulatory agency or a federal-provincial regulatory agency that has administrative responsibility for the exploration for and exploitation of oil and gas in an area adjoining the perimeter; (organisme de réglementation)

royalty interest

royalty interest means any interest in, or the right to receive a portion of, any oil or gas produced and saved from a field or pool or part of a field or pool or the proceeds from the sale thereof, but does not include a working interest or the interest of any person whose sole interest is as a purchaser of oil or gas from the pool or part thereof; (droit à redevance)

royalty owner

royalty owner means a person, including Her Majesty in right of Canada, who owns a royalty interest; (titulaire de redevance)

spacing unit

spacing unit means the area allocated to a well for the purpose of drilling for or producing oil or gas; (unité d’espacement)

tract participation

tract participation means the share of production from a unitized zone that is allocated to a unit tract under a unit agreement or unitization order or the share of production from a pooled spacing unit that is allocated to a pooled tract under a pooling agreement or pooling order; (fraction parcellaire)

transboundary

transboundary means, in relation to a pool, extending beyond the Commission of the Canadian Energy Regulator’s jurisdiction under this Act or, in relation to a field, underlain only by one or more such pools; (transfrontalier)

unit agreement

unit agreement means an agreement to unitize the interests of owners in a pool or a part of a pool exceeding in area a spacing unit, or such an agreement as varied by a unitization order; (accord d’union)

unit area

unit area means the area that is subject to a unit agreement; (secteur unitaire)

unitization order

unitization order means an order made under section 41, 48.092 or 48.23; (arrêté d’union)

unitized zone

unitized zone means a geological formation that is within a unit area and subject to a unit agreement; (terrain)

unit operating agreement

unit operating agreement means an agreement, providing for the management and operation of a unit area and a unitized zone, that is entered into by working interest owners who are parties to a unit agreement with respect to that unit area and unitized zone, and includes a unit operating agreement as varied by a unitization order; (accord d’exploitation unitaire)

unit operation

unit operation means those operations conducted pursuant to a unit agreement or a unitization order; (exploitation unitaire)

unit operator

unit operator means a person designated as a unit operator under a unit operating agreement; (exploitant unitaire)

unit tract

unit tract means the portion of a unit area that is defined as a tract in a unit agreement; (parcelle unitaire)

working interest

working interest means a right, in whole or in part, to produce and dispose of oil or gas from a pool or part of a pool, whether that right is held as an incident of ownership of an estate in fee simple in the oil or gas or under a lease, agreement or other instrument, if the right is chargeable with and the holder thereof is obligated to pay or bear, either in cash or out of production, all or a portion of the costs in connection with the drilling for, recovery and disposal of oil or gas from the pool or part thereof; (intérêt économique direct)

working interest owner

working interest owner means a person who owns a working interest. (détenteur)

  • R.S., 1985, c. O-7, s. 29
  • 1992, c. 35, s. 27(F)
  • 2014, c. 2, s. 24
  • 2015, c. 4, ss. 23, 118
  • 2019, c. 28, s. 142
.

Pooling

Marginal note:Voluntary pooling

  •  (1) Where one or more working interest owners have leases or separately owned working interests within a spacing unit, the working interest owners and the royalty owners who own all of the interests in the spacing unit may pool their working interests and royalty interests in the spacing unit for the purpose of drilling for or producing, or both drilling for and producing, oil and gas if a copy of the pooling agreement and any amendment thereto has been filed with the Chief Conservation Officer.

  • Marginal note:Pooling agreement by Her Majesty

    (2) The Minister may, on behalf of Her Majesty, enter into a pooling agreement on any terms and conditions that the Minister deems advisable and, despite anything in this Act, the Territorial Lands Act, the Federal Real Property and Federal Immovables Act, the Canada Petroleum Resources Act or any regulations made under those Acts, the pooling agreement is binding on Her Majesty.

  • R.S., 1985, c. O-7, s. 30
  • R.S., 1985, c. 36 (2nd Supp.), s. 124
  • 1991, c. 50, s. 35
  • 2001, c. 4, s. 163
.

Marginal note:Application for pooling order

  •  (1) In the absence of a pooling agreement, a working interest owner in a spacing unit may apply for a pooling order directing the working interest owners and royalty owners within the spacing unit to pool their interests in the spacing unit for the purpose of drilling for and producing, or producing, oil or gas or both from the spacing unit.

  • Marginal note:Hearing by Committee

    (2) An application under subsection (1) shall be made to the Minister who shall refer the application to the Committee for the purpose of holding a hearing to determine whether a pooling order should be made and at that hearing the Committee shall afford all interested parties an opportunity to be heard.

  • Marginal note:Matter to be supplied Committee on hearing

    (3) Prior to a hearing held pursuant to subsection (2), the working interest owner making application shall provide the Committee, and such other interested parties as the Committee may direct, with a proposed form of pooling agreement, and the working interest owners who have interests in the spacing unit to which the proposed pooling agreement relates shall provide the Committee with such information as the Committee deems necessary.

  • Marginal note:Order of Committee

    (4) After a hearing held pursuant to subsection (2), the Committee may order that all working interest owners and royalty owners who have an interest in the spacing unit shall be deemed to have entered into a pooling agreement as set out in the pooling order.

  • R.S., c. O-4, s. 22
.

Marginal note:Contents of pooling order

 Every pooling order shall provide

  • (a) for the drilling and operation of a well on the spacing unit or, where a well that is capable of or that can be made capable of production has been drilled on the spacing unit before the making of the pooling order, for the future production and operation of that well;

  • (b) for the appointment of a working interest owner as operator to be responsible for the drilling, operation or abandoning of the well whether drilled before or after the making of the pooling order;

  • (c) for the allocation to each pooled tract of its share of the production of the oil or gas from the pooled spacing unit that is not required, consumed or lost in the operation of the well, which allocation shall be on a prorated area basis unless it can be shown to the satisfaction of the Committee that that basis is unfair, whereupon the Committee may make an allocation on another more equitable basis;

  • (d) in the event that no production of oil or gas is obtained, for the payment by the applicant therefor of all costs incurred in the drilling and abandoning of the well;

  • (e) where production has been obtained, for the payment of the actual costs of drilling the well, whether drilled before or after the making of the pooling order, and for the payment of the actual costs of the completion, operation and abandoning of the well; and

  • (f) for the sale by the operator of any oil or gas allocated pursuant to paragraph (c) to a working interest owner where the working interest owner thereof fails to take in kind and dispose of the production, and for the deduction out of the proceeds by the operator of his expenses reasonably incurred in connection with the sale.

  • R.S., c. O-4, s. 22
  • 1976-77, c. 55, s. 5(E)
.

Marginal note:Provision of penalty

  •  (1) A pooling order may provide for a penalty for a working interest owner who does not, within the time specified in the order, pay the portion of the costs attributable to him as his share of the cost of drilling and completion of the well, but the penalty shall not exceed an amount equal to one-half of that working interest owner’s share of those costs.

  • Marginal note:Recovery of costs and penalty

    (2) If a working interest owner does not, within the time specified therefor in the pooling order, pay his share of the costs of the drilling, completing, operating and abandoning of the well, his portion of the costs and the penalty, if any, are recoverable only out of his share of production from the spacing unit and not in any other manner.

  • R.S., c. O-4, s. 22
.

Marginal note:Effect of pooling order

 Where a pooling order is made, all working interest owners and royalty owners having interests in the pooled spacing unit shall, on the making of the order, be deemed to have entered into a pooling agreement as set out in the pooling order and the order shall be deemed to be a valid contract between the parties having interests in the pooled spacing unit, and all its terms and provisions, as set out therein or as altered pursuant to section 35, are binding on and enforceable against the parties thereto, including Her Majesty.

  • R.S., c. O-4, s. 23
.

Marginal note:Application to alter pooling order

  •  (1) The Committee shall hear any application to vary, amend or terminate a pooling order where the application is made by the owners of over twenty-five per cent of the working interests in the pooled spacing unit, calculated on a prorated area basis, and may, in its discretion, order a hearing on the application of any working interest owner or royalty owner.

  • Marginal note:Alteration of pooling order

    (2) After a hearing held pursuant to subsection (1), the Committee may vary or amend the pooling order to supply any deficiency therein or to meet changing conditions and may vary or revoke any provision that the Committee deems to be unfair or inequitable or it may terminate the pooling order.

  • Marginal note:Tract participation ratios protected

    (3) Where a pooling order is varied or amended, no change shall be made that will alter the ratios of tract participations between the pooled tracts as originally set out in the pooling order.

  • R.S., c. O-4, s. 24
  • 1976-77, c. 55, s. 5(E)
.

Marginal note:Prohibition

  •  (1) No person shall produce any oil or gas within a spacing unit in which there are two or more leases or two or more separately owned working interests unless a pooling agreement has been entered into in accordance with section 30 or in accordance with a pooling order made under section 31.

  • Marginal note:Saving

    (2) Subsection (1) does not prohibit the production of oil or gas for testing in any quantities approved by the Chief Conservation Officer.

  • R.S., c. O-4, s. 25
  • 1980-81-82-83, c. 81, s. 75(F)
.

Unitization

Marginal note:Unit operation

  •  (1) Any one or more working interest owners in a pool or part of a pool exceeding in area a spacing unit, together with the royalty owners, may enter into a unit agreement and operate their interests pursuant to the terms of the unit agreement or any amendment thereto if a copy of the agreement and any amendment has been filed with the Chief Conservation Officer.

  • Marginal note:Minister may enter into unit agreement

    (2) The Minister may enter into a unit agreement binding on Her Majesty, on any terms and conditions that the Minister may deem advisable, and any of the regulations under this Act, the Territorial Lands Act, the Federal Real Property and Federal Immovables Act or the Canada Petroleum Resources Act that may be in conflict with the terms and conditions of the unit agreement stand varied or suspended to the extent necessary to give full effect to the terms and conditions of the unit agreement.

  • Marginal note:Unit operator’s relationship to parties

    (3) Where a unit agreement filed under this section provides that a unit operator shall be the agent of the parties thereto with respect to their powers and responsibilities under this Act, the performance or non-performance thereof by the unit operator shall be deemed to be the performance or non-performance by the parties otherwise having those powers and responsibilities under this Act.

  • R.S., 1985, c. O-7, s. 37
  • R.S., 1985, c. 36 (2nd Supp.), s. 125
  • 1991, c. 50, s. 36
  • 2001, c. 4, s. 164
.

Marginal note:Requiring unitization to prevent waste

  •  (1) Notwithstanding anything in this Act, where, in the opinion of the Chief Conservation Officer, the unit operation of a pool or part thereof would prevent waste, he may apply to the Committee for an order requiring the working interest owners in the pool or part thereof to enter into a unit agreement and a unit operating agreement in respect of the pool or part thereof, as the case may be.

  • Marginal note:Hearing

    (2) Where an application is made by the Chief Conservation Officer pursuant to subsection (1), the Committee shall hold a hearing at which all interested persons shall be afforded an opportunity to be heard.

  • Marginal note:Order

    (3) If, after the hearing mentioned in subsection (2), the Committee is of the opinion that the unit operation of a pool or part thereof would prevent waste, the Committee may by order require the working interest owners in the pool or part thereof to enter into a unit agreement and a unit operating agreement in respect of the pool or part thereof.

  • Marginal note:Cessation of operations

    (4) If in the time specified in the order referred to in subsection (3), being not less than six months after the date of the making of the order, the working interest owners and royalty owners fail to enter into a unit agreement and a unit operating agreement approved by the Committee, all drilling and producing operations within the pool or part thereof in respect of which the order was made shall cease until such time as a unit agreement and a unit operating agreement have been approved by the Committee and filed with the Chief Conservation Officer.

  • Marginal note:Permit to continue operations

    (5) Notwithstanding subsection (4), the Committee may permit the continued operation of the pool or part thereof after the time specified in the order referred to in subsection (3) if it is of the opinion that a unit agreement and unit operating agreement are in the course of being entered into, but any such continuation of operations shall be subject to any conditions prescribed by the Committee.

  • R.S., c. O-4, s. 27
.

Compulsory Unitization

Marginal note:Who may apply for unitization order

  •  (1) One or more working interest owners who are parties to a unit agreement and a unit operating agreement and own in the aggregate sixty-five per cent or more of the working interests in a unit area may apply for a unitization order with respect to the agreements.

  • Marginal note:Application for unitization order

    (2) An application under subsection (1) shall be made to the Minister who shall refer the application to the Committee for the purpose of holding a hearing thereon in accordance with section 41.

  • Marginal note:Application by proposed unit operator

    (3) An application under subsection (1) may be made by the unit operator or proposed unit operator on behalf of the working interest owners referred to in that subsection.

  • R.S., c. O-4, s. 28
.

Marginal note:Contents of unitization application

  •  (1) An application for a unitization order shall contain

    • (a) a plan showing the unit area that the applicant desires to be made subject to the order;

    • (b) one copy each of the unit agreement and the unit operating agreement;

    • (c) a statement of the nature of the operations to be carried out; and

    • (d) a statement showing

      • (i) with respect to each proposed unit tract, the names and addresses of the working interest owners and royalty owners in that tract, and

      • (ii) the tracts that are entitled to be qualified as unit tracts under the provisions of the unit agreement.

  • Marginal note:Details required of unit agreement

    (2) The unit agreement referred to in subsection (1) shall include

    • (a) a description of the unit area and the unit tracts included in the agreement;

    • (b) an allocation to each unit tract of a share of the production from the unitized zone not required, consumed or lost in the unit operation;

    • (c) a provision specifying the manner in which and the circumstances under which the unit operation shall terminate; and

    • (d) a provision specifying that the share of the production from a unit area that has been allocated to a unit tract shall be deemed to have been produced from that unit tract.

  • Marginal note:Details required of unit operating agreement

    (3) The unit operating agreement referred to in subsection (1) shall make provision

    • (a) for the contribution or transfer to the unit, and any adjustment among the working interest owners, of the investment in wells and equipment within the unit area;

    • (b) for the charging of the costs and expenses of the unit operation to the working interest owners;

    • (c) for the supervision of the unit operation by the working interest owners through an operating committee composed of their duly authorized representatives and for the appointment of a unit operator to be responsible, under the direction and supervision of the operating committee, for the carrying out of the unit operation;

    • (d) for the determination of the percentage value of the vote of each working interest owner; and

    • (e) for the determination of the method of voting on any motion before the operating committee and the percentage value of the vote required to carry the motion.

  • R.S., c. O-4, s. 29
.

Marginal note:Hearing on application

  •  (1) Where an application made under section 39 is referred by the Minister to the Committee, the Committee shall hold a hearing thereon at which all interested persons shall be afforded an opportunity to be heard.

  • Marginal note:Unitization order

    (2) If the Committee finds that

    • (a) at the date of the commencement of a hearing referred to in subsection (1)

      • (i) the unit agreement and the unit operating agreement have been executed by one or more working interest owners who own in the aggregate sixty-five per cent or more of the total working interests in the unit area, and

      • (ii) the unit agreement has been executed by one or more royalty owners who own in the aggregate sixty-five per cent or more of the total royalty interests in the unit area, and

    • (b) the unitization order applied for would accomplish the more efficient or more economical production of oil or gas or both from the unitized zone,

    the Committee may order

    • (c) that the unit agreement be a valid contract enuring to the benefit of all the royalty owners and working interest owners in the unit area and binding on and enforceable against all such owners, and

    • (d) that the unit operating agreement be a valid contract enuring to the benefit of all the working interest owners in the unit area and binding on and enforceable against all such owners,

    and, subject to section 42, the unit agreement and the unit operating agreement have the effect given them by the order of the Committee.

  • Marginal note:Variation by unitization order

    (3) In a unitization order, the Committee may vary the unit agreement or the unit operating agreement by adding provisions or by deleting or amending any provision thereof.

  • R.S., c. O-4, s. 30
.

Marginal note:Effective date of unitization order

  •  (1) Subject to subsection (2), a unitization order becomes effective on the day that the Committee determines in the order, but that day shall be not less than thirty days after the day on which the order is made.

  • Marginal note:Effective date when unit agreement or unit operating agreement varied

    (2) Where a unit agreement or unit operating agreement is varied by the Committee in a unitization order, the effective date prescribed in the order shall be a date not less than thirty days following the day the order is made, but the order becomes ineffective if, before the effective date, the applicant files with the Committee a notice withdrawing the application on behalf of the working interest owners or there are filed with the Committee statements in writing objecting to the order and signed

    • (a) in the case of the unit agreement, by

      • (i) one or more working interest owners who own in the aggregate more than twenty-five per cent of the total working interests in the area and were included within the group owning sixty-five per cent or more of the total working interests as described in subparagraph 41(2)(a)(i), and

      • (ii) one or more royalty owners who own in the aggregate more than twenty-five per cent of the total royalty interests in the unit area and were included within the group owning sixty-five per cent or more of the total royalty interests as described in subparagraph 41(2)(a)(ii); or

    • (b) in the case of the unit operating agreement, by one or more working interest owners who own in the aggregate more than twenty-five per cent of the total working interests in the unit area and were included within the group owning sixty-five per cent or more of the total working interests as described in subparagraph 41(2)(a)(i).

  • Marginal note:Revocation of order

    (3) Where a unitization order becomes ineffective under subsection (2), the Committee shall forthwith revoke the order.

  • R.S., 1985, c. O-7, s. 42
  • 1992, c. 35, s. 28(E)
.

Marginal note:Technical defects in unitization order

 A unitization order is not invalid by reason only of the absence of notice or of any irregularities in giving notice to any owner in respect of the application for the order or any proceedings leading to the making of the order.

  • R.S., c. O-4, s. 32
.

Marginal note:Amending unitization order

  •  (1) A unitization order may be amended on the application of a working interest owner, but before amending a unitization order the Committee shall hold a hearing at which all interested parties shall have an opportunity to be heard.

  • Marginal note:Voluntary proposal for amendment by owners

    (2) If the Committee finds that, at the date of the commencement of a hearing of an application for the amendment of a unitization order, one or more working interest owners who own, in the aggregate, sixty-five per cent or more of the total working interests and one or more royalty interest owners who own, in the aggregate, sixty-five per cent or more of the total royalty interests in the unit area have consented to the proposed amendment, the Committee may amend the unitization order in accordance with the amendment proposed.

  • R.S., c. O-4, s. 33
.

Marginal note:Protection of tract participation ratios

 No amendment shall be made under section 44 that will alter the ratios between the tract participations of those tracts that were qualified for inclusion in the unit area before the commencement of the hearing, and, for the purposes of this section, the tract participations shall be those indicated in the unit agreement when it became subject to a unitization order.

  • R.S., c. O-4, s. 34
.

Marginal note:Production prohibited except in accord with unitization order

 After the date on which a unitization order comes into effect and while the order remains in force, no person shall carry on any operations within the unit area for the purpose of drilling for or producing oil or gas from the unitized zone, except in accordance with the provisions of the unit agreement and the unit operating agreement.

  • R.S., c. O-4, s. 35
.

Marginal note:How percentages of interests to be determined

  •  (1) The percentages of interests referred to in subsections 39(1), 41(2), 42(2) and 44(2) shall be determined

    • (a) with respect to royalty interests, on a prorated area basis; and

    • (b) with respect to working interests, on the basis of tract participations shown in the unit agreement.

  • Marginal note:Owner deemed to be royalty owner on a prorated area basis

    (2) Where a working interest in a unit tract is held as an incident of the ownership of a fee simple estate in oil or gas, the owner who holds that working interest shall, for the purposes of subsection (1), be deemed to be a royalty owner in respect of the tract on a prorated area basis under paragraph (1)(a).

  • R.S., c. O-4, s. 36
  • 1976-77, c. 55, s. 5(E)
.

General

Marginal note:Pooled spacing unit included in unit area

  •  (1) A pooled spacing unit that has been pooled pursuant to a pooling order and on which a well has been drilled may be included in a unit area as a single unit tract and the Committee may make such amendments to the pooling order as it deems necessary to remove any conflict between the provisions of the pooling order and the provisions of the unit agreement, or the unit operating agreement or the unitization order, if any.

  • Marginal note:Effect of including pooled spacing unit in unit area

    (2) Where a pooled spacing unit is included in a unit area pursuant to subsection (1), the provisions of the unit agreement, the unit operating agreement and the unitization order, if any, prevail over the provisions of the pooling order in the event of a conflict.

  • Marginal note:Exceptions

    (3) Notwithstanding subsection (2),

    • (a) the share of the unit production that is allocated to the pooled spacing unit shall in turn be allocated to the separately owned tracts in the pooled spacing unit on the same basis and in the same proportion as production actually obtained from the pooled spacing unit would have been shared under the pooling order;

    • (b) the costs and expenses of the unit operation that are allocated to the pooled spacing unit shall be shared and borne by the owners of the working interests therein on the same basis and in the same proportion as would apply under the pooling order; and

    • (c) the credits allocated under a unit operating agreement to a pooled spacing unit for adjustment of investment for wells and equipment thereon shall be shared by the owners of the working interests therein in the same proportion as would apply to the sharing of production under the pooling order.

  • R.S., c. O-4, s. 37
.

Straddling Resources — Inuvialuit Settlement Region

Definitions

Marginal note:Definitions

 The following definitions apply in this section and in sections 48.02 to 48.096.

notification area

notification area means the following:

  • (a) that part of the offshore that is situated within 20 kilometres of the onshore; and

  • (b) that part of the onshore that is situated within 20 kilometres of the offshore. (zone de notification)

offshore

offshore means that part of the Inuvialuit Settlement Region that is not situated in the onshore. (région extracôtière)

  • 2014, c. 2, s. 25
.

Determination

Marginal note:Commission of the Canadian Energy Regulator’s obligations

 If the data obtained from conducting a survey or drilling an exploratory well — as defined in subsection 101(1) of the Canada Petroleum Resources Act — in the notification area provide sufficient information for the Commission of the Canadian Energy Regulator to determine that a pool or field exists, the Commission shall

  • (a) determine whether the pool or field is a straddling resource;

  • (b) without delay notify the Minister and the Government of the Northwest Territories of its determination and the reasons for it; and

  • (c) on request, provide that Minister or that Government with the information that is in the Commission’s possession and pertinent to that determination.

  • 2014, c. 2, s. 25
  • 2019, c. 28, s. 142
.

Marginal note:Information sharing

 The Minister and the Government of the Northwest Territories shall, on request, provide the other with the information that is in their possession and is relevant to the proper and efficient exploration for and the management, administration and exploitation of the straddling resource.

  • 2014, c. 2, s. 25
.

Exploitation of Straddling Resources

Marginal note:Single pool or field

  •  (1) A straddling resource may be exploited as a single pool or field, as the case may be.

  • Marginal note:Single exploration or drilling program

    (2) An exploration or drilling program related to a straddling resource is, to the extent practicable, to be managed as a single exploration or drilling program.

  • 2014, c. 2, s. 25
.

Marginal note:Notice — intention to start production

  •  (1) If an interest owner, as defined in section 2 of the Canada Petroleum Resources Act, advises the Minister or the Commission of the Canadian Energy Regulator — including by way of an application under section 38 of the Canada Petroleum Resources Act or paragraph 5(1)(b) of this Act, as the case may be — that it intends to start production of a straddling resource, the Minister shall, without delay, notify the Government of the Northwest Territories of the interest owner’s intention.

  • Marginal note:Notice — after production commences

    (2) If, after production commences, the Commission of the Canadian Energy Regulator determines that a pool or field is a straddling resource

    • (a) the Minister or the Government of the Northwest Territories — depending on the jurisdiction in which production commenced — shall, without delay, notify the other of that determination; and

    • (b) either of them may give notice under section 48.06.

  • 2014, c. 2, s. 25
  • 2019, c. 28, s. 142
.

Marginal note:Requirement — exploitation as single unit

 The Minister or the Government of the Northwest Territories may, by notice, require of the other that a pool or field that is a straddling resource be exploited as a single pool or field, as the case may be.

  • 2014, c. 2, s. 25
.

Marginal note:Unit agreement

  •  (1) The royalty owners and the working interest owners in respect of a straddling resource may enter into a unit agreement and, if it is approved under subsection 48.09(1), they shall operate their interests in accordance with it or any amendment to it.

  • Marginal note:Unit operating agreement

    (2) The working interest owners in respect of a straddling resource may enter into a unit operating agreement and, if it is approved under subsection 48.09(1), they shall operate their interests in accordance with it or any amendment to it.

  • Marginal note:Termination

    (3) Unless the Minister and the Government of the Northwest Territories agree to an earlier termination, a unit agreement or a unit operating agreement remains in force until the later of

    • (a) the day on which commercial production from the straddling resources to which the agreement applies ends, and

    • (b) the day on which there are no outstanding obligations in respect of the decommissioning or the abandonment of the production system for a straddling resource to which the agreement applies.

  • 2014, c. 2, s. 25
.

Marginal note:Order to enter into agreements

 If a straddling resource is required to be exploited as a single pool or field under section 48.06 and the working interest owners have not entered into a unit agreement and a unit operating agreement, the Minister shall order the working interest owners in the portion of the pool or field that is in the Minister’s jurisdiction to do so.

  • 2014, c. 2, s. 25
.

Marginal note:Approval of agreements

  •  (1) A unit agreement and a unit operating agreement are subject to the approval of the Minister and the Government of the Northwest Territories. They are to be approved only if all royalty owners and working interest owners referred to in subsection 48.07(1) or all working interest owners referred to in subsection 48.07(2), as the case may be, are parties to the agreement.

  • Marginal note:Condition precedent

    (2) No authorization is to be issued under paragraph 5(1)(b) — and no development plan is to be approved under subsection 5.1(4) — in relation to the exploitation of a straddling resource if the unit agreement and the unit operating agreement are not approved under subsection (1).

  • 2014, c. 2, s. 25
.

Marginal note:Referral to independent expert

 If the royalty owners and the working interest owners in respect of a straddling resource do not enter into a unit agreement — and, in the case of the working interest owners, a unit operating agreement — within 90 days after the day on which the Minister orders the working interest owners to enter into those agreements under section 48.08, the Minister or the Government of the Northwest Territories may notify the other of their intention to refer the matter to an independent expert for a decision in accordance with section 48.095.

  • 2014, c. 2, s. 25
.

Marginal note:Unitization order

  •  (1) The Minister shall issue a unitization order in accordance with the independent expert’s final decision.

  • Marginal note:Effect

    (2) The unit agreement and the unit operating agreement have the effect given them by the Minister’s order.

  • Marginal note:Government of the Northwest Territories

    (3) A unitization order becomes effective only if the Government of the Northwest Territories issues an equivalent order.

  • Marginal note:Joint approval

    (4) The issuance of a unitization order by the Minister and of an equivalent order by the Government of the Northwest Territories is deemed to be their joint approval of the unit agreement and the unit operating agreement.

  • Marginal note:Effective date

    (5) Subject to subsection (3), a unitization order becomes effective on the day established in the order, but that day is not to be less than 30 days after the day on which the order is issued.

  • 2014, c. 2, s. 25
.

Marginal note:Redetermination

 The Minister, the Government of the Northwest Territories or a working interest owner may — in respect of future production — request a redetermination of

  • (a) the apportionment of the production from the straddling resource; or

  • (b) one or more of the elements set out in the unit agreement or the unit operating agreement.

  • 2014, c. 2, s. 25
.

Marginal note:No agreement — royalty owners and working interest owners

 If the royalty owners and the working interest owners in respect of a straddling resource do not enter into an agreement in respect of the redetermination under section 48.093 within 90 days after the day on which the request is made, the Minister or the Government of the Northwest Territories may notify the other of their intention to refer the matter to an independent expert for a decision in accordance with section 48.095.

  • 2014, c. 2, s. 25
.

Marginal note:Independent expert

  •  (1) Within 90 days after the day on which the Minister or the Government of the Northwest Territories is notified under subsection 5.1(8) or section 48.091 or 48.094, the Minister and the Government shall appoint the independent expert.

  • Marginal note:Qualifications

    (2) The independent expert must be impartial and independent and have knowledge or experience relevant to the matter.

  • Marginal note:Appointment — drawing lots

    (3) If the Minister and the Government of the Northwest Territories do not appoint the expert in accordance with subsection (1), each shall — within 30 days after the day on which the time to appoint an expert expires — submit to the other the names of up to two persons with the qualifications set out in subsection (2); they shall within 30 days after the day of submission select the independent expert from those persons by drawing lots and appoint that person as the independent expert.

  • Marginal note:Absence of submission, selection or appointment

    (4) If the Minister or the Government of the Northwest Territories does not submit, select or appoint as required by subsection (3), they are deemed to make the same submission, selection or appointment — as the case may be — as the other and are bound by the decision of the independent expert.

  • Marginal note:Preliminary decision

    (5) Within 90 days after the day on which they are seized of the matter or within any other period agreed to by the Minister and the Government of the Northwest Territories, the independent expert shall render a preliminary decision and the Minister and the Government are to be provided with it and the reasons for it, including any supporting documentation.

  • Marginal note:Clarification or reconsideration

    (6) The Minister or the Government of the Northwest Territories may — within 60 days after being provided with the preliminary decision — request the independent expert to clarify or reconsider that decision and make additional submissions to the independent expert.

  • Marginal note:Further submissions

    (7) If the Minister or the Government of the Northwest Territories does so request and make such submissions, they shall provide the other with a copy of those submissions. The other may — within 15 days after the day on which they receive that copy — make further submissions and shall provide the other with a copy of them.

  • Marginal note:Final decision

    (8) Within 120 days after the day on which they render a preliminary decision, the independent expert shall render a final decision and the Minister and the Government of the Northwest Territories are to be provided with it and the reasons for it, including any supporting documentation.

  • Marginal note:Decision is final and binding

    (9) An independent expert’s final decision is final and binding on the Minister and the Government of the Northwest Territories and is not to be challenged on appeal or judicial review in any court except on the ground that the independent expert erred in law or exceeded the independent expert’s jurisdiction.

  • Marginal note:Legal proceedings

    (10) If a person acts as an independent expert,

    • (a) the person is not to be called to give evidence, and is not compellable as a witness, in any legal proceedings related to the matter; and

    • (b) the person’s records related to the matter are not admissible as evidence in any legal proceedings related to the matter.

  • 2014, c. 2, s. 25
.

Marginal note:Regulations — Inuvialuit lands

 The Governor in Council may, if the Inuvialuit Regional Corporation agrees in writing under subsection 3.3(b) of the Agreement to be bound by a provision of Article 5 of the Agreement, make regulations adapting the definitions Agreement, Inuvialuit Settlement Region and straddling resource in section 2 and sections 48.01 to 48.095 accordingly.

  • 2014, c. 2, s. 25
.

Transboundary Pools or Fields

Delineation

Marginal note:Appropriate regulator

 For the purposes of sections 48.11 to 48.14, the appropriate regulator is any regulator that has jurisdiction in an area

  • (a) adjoining the portion of the perimeter where the drilling took place or where an accumulation of oil or gas exists; or

  • (b) into which there is reason to believe that, based on the data obtained from any drilling, an accumulation of oil or gas extends.

  • 2015, c. 4, s. 24
.

Marginal note:Information

  •  (1) If an exploratory well, as defined in subsection 101(1) of the Canada Petroleum Resources Act, is drilled in the perimeter, the Commission of the Canadian Energy Regulator shall provide each appropriate regulator, within the prescribed time and in the prescribed manner, with any information in its possession, including any prescribed information, that is relevant to the determination of whether a pool is transboundary and its delineation.

  • Marginal note:Additional information

    (2) The Commission of the Canadian Energy Regulator shall, on request, provide the regulator with any additional information in its possession, that is relevant to the determination of whether a pool is transboundary and its delineation.

  • 2015, c. 4, s. 24
  • 2019, c. 28, s. 142
.

Marginal note:Notice — as soon as feasible

  •  (1) If the data obtained from any drilling in the perimeter provides sufficient information for the Commission of the Canadian Energy Regulator to determine whether a pool exists, the Commission shall notify each appropriate regulator as soon as feasible of its determination.

  • Marginal note:Notice — after three drillings

    (2) If no notice is given under subsection (1), the Commission of the Canadian Energy Regulator shall, no later than one year after the day on which it receives data from the last of three drillings of the same geological feature in the perimeter, notify each appropriate regulator of its determination or that there is insufficient information to make a determination based on the data from those drillings.

  • Marginal note:Notice — transboundary pool

    (3) If the Commission of the Canadian Energy Regulator determines that a pool exists, the Commission shall also specify in the notice whether or not there is, in its opinion, reason to believe that the pool is transboundary.

  • Marginal note:Reasons

    (4) The Commission of the Canadian Energy Regulator shall provide each appropriate regulator and the Minister with the reasons for its determination and opinion.

  • 2015, c. 4, s. 24
  • 2019, c. 28, s. 142
.

Marginal note:Notice from Canadian Energy Regulator

  •  (1) If the Canadian Energy Regulator receives a notice from a regulator indicating the regulator’s determination as to whether a pool exists in an area adjoining the perimeter and, if applicable, whether there is reason to believe the pool extends into the perimeter, the Commission of the Canadian Energy Regulator shall, within 90 days after the day on which the notice is received, inform the regulator of its agreement or disagreement with the content of the notice.

  • Marginal note:Reasons

    (2) If the Commission of the Canadian Energy Regulator disagrees with the content of the notice, it shall provide the regulator with the reasons for its disagreement.

  • 2015, c. 4, s. 24
  • 2019, c. 28, s. 136
  • 2019, c. 28, s. 142
.

Marginal note:Delineation

  •  (1) If, after receiving a notice under section 48.12 or 48.13, the Commission of the Canadian Energy Regulator and the regulator in question agree that a pool exists, the Commission and that regulator shall jointly determine whether that pool is transboundary and, if so, they shall jointly delineate its boundaries.

  • Marginal note:Disagreement

    (2) The Commission of the Canadian Energy Regulator or the regulator may, if they disagree about whether a pool exists, whether the pool is transboundary or its delineation, refer the matter to an expert, no later than 180 days after the day on which the Commission issues a notice under section 48.12, or the regulator issues an equivalent notice.

  • 2015, c. 4, s. 24
  • 2019, c. 28, s. 142
.

Agreements Relating to Development

Marginal note:Appropriate regulator

 For the purposes of sections 48.16 to 48.27, the appropriate regulator is the regulator that has jurisdiction in an area into which the transboundary pool or field in question extends.

  • 2015, c. 4, s. 24
.

Marginal note:Joint exploitation agreement

 The Minister and the appropriate regulator may enter into a joint exploitation agreement providing for the development of a transboundary pool or field as a single field. The agreement shall include any matters provided for by regulation.

  • 2015, c. 4, s. 24
.

Marginal note:Development as a single field

  •  (1) If a joint exploitation agreement has been entered into, the transboundary pool or field may only be developed as a single field. The development of that field is subject to the following agreements having been entered into and subsequently approved under subsection 48.2(2) or 48.23(4):

    • (a) a unit agreement that includes the details referred to in paragraphs 40(2)(a) to (d); and

    • (b) a unit operating agreement that includes the details referred to in paragraphs 40(3)(a) to (e).

  • Marginal note:Joint exploitation agreement prevails

    (2) The joint exploitation agreement prevails over the unit agreement and the unit operating agreement to the extent of any inconsistency between them.

  • 2015, c. 4, s. 24
.

Marginal note:Intention to start production

  •  (1) If an interest owner — as defined in the Canada Petroleum Resources Act — advises the Minister or the Canadian Energy Regulator, including by way of an application under paragraph 5(1)(b) of this Act or under section 38 of the Canada Petroleum Resources Act, that it intends to start production from a transboundary pool or field, the Minister shall notify the appropriate regulator as soon as feasible of the interest owner’s intention.

  • Marginal note:Referral to expert

    (2) If the Minister and the regulator have attempted to enter into a joint exploitation agreement but have been unsuccessful, the Minister or the regulator may, 180 days after the day on which the Minister gives notice under subsection (1), refer the matter to an expert to determine the particulars of the agreement. They may, however, agree to refer the matter to an expert at any time before the end of those 180 days.

  • 2015, c. 4, s. 24
  • 2019, c. 28, s. 142
.

Marginal note:Unit agreement

  •  (1) The royalty owners and the working interest owners in a transboundary pool or field that is to be developed as a single field may enter into a unit agreement and, once approved, shall operate their interests in accordance with it, including any amendment to it.

  • Marginal note:Applicable provisions

    (2) Subsections 37(2) and (3) apply to the unit agreement.

  • 2015, c. 4, s. 24
.

Marginal note:Condition precedent

  •  (1) A unit agreement and unit operating agreement are to be jointly approved by the Minister and the appropriate regulator before an authorization is issued under paragraph 5(1)(b) for a work or activity proposed to be carried on in relation to the development of a transboundary pool or field as a single field.

  • Marginal note:Approval

    (2) The Minister and the appropriate regulator may approve the unit agreement if all the royalty owners and all the working interest owners in the pool or field are parties to it; the Minister and the appropriate regulator may approve the unit operating agreement if all the working interest owners in the pool or field are parties to it.

  • 2015, c. 4, s. 24
.

Marginal note:Application for unitization order

  •  (1) One or more working interest owners who are parties to a unit agreement and a unit operating agreement and own in total 65% or more of the working interests in a transboundary pool or field that is to be developed as a single field may apply for a unitization order with respect to the agreements.

  • Marginal note:Contents

    (2) The application shall be submitted to both the Minister and the appropriate regulator. It shall include the documents and statements referred to in subsection 40(1) and may be made by the unit operator or proposed unit operator on behalf of the working interest owners.

  • Marginal note:Appointment of expert

    (3) The Minister and the regulator shall, for the purposes of section 48.22, appoint an expert in accordance with subsections 48.27(2) to (4).

  • 2015, c. 4, s. 24
.

Marginal note:Hearing

  •  (1) Once seized of an application made under section 48.21, the expert shall hold a hearing at which all interested persons shall be given an opportunity to be heard.

  • Marginal note:Conclusion of hearing

    (2) On the conclusion of the hearing, the expert shall request that the Minister and the appropriate regulator

    • (a) order that the unit agreement is a valid contract enuring to the benefit of all the royalty owners and working interest owners who have an interest in the unit area and binding on and enforceable against all such owners, and that the unit operating agreement is a valid contract enuring to the benefit of all the working interest owners who have an interest in the unit area and binding on and enforceable against all such owners; and

    • (b) include in the order any variations to the unit agreement or unit operating agreement that the expert determines are necessary to allow for the more efficient or more economical production of oil or gas from the unitized zone.

  • Marginal note:Exception

    (3) Despite subsection (2), the expert shall end the hearing and request that the Minister and the appropriate regulator take the measure outlined in paragraph (2)(a) if the expert finds that,

    • (a) on the day on which the hearing begins,

      • (i) the unit agreement and the unit operating agreement have been executed by one or more working interest owners who own in total 65% or more of the total working interests in the unit area, and

      • (ii) the unit agreement has been executed by one or more royalty owners who own in total 65% or more of the total royalty interests in the unit area; and

    • (b) the unitization order applied for would allow for the more efficient or more economical production of oil or gas from the unitized zone.

  • 2015, c. 4, s. 24
.

Marginal note:Unitization order

  •  (1) The Minister shall issue an order in accordance with the expert’s request under subsection 48.22(2) or (3).

  • Marginal note:Effect of unitization order

    (2) The unit agreement and the unit operating agreement have the effect given to them by the Minister’s order.

  • Marginal note:Equivalent order

    (3) A unitization order becomes effective only if the appropriate regulator has issued an equivalent order.

  • Marginal note:Joint approval

    (4) The issuance of a unitization order by the Minister and of an equivalent order by the regulator is deemed to be their joint approval of the unit agreement and the unit operating agreement.

  • Marginal note:Effective date of unitization order

    (5) Subject to subsections (3) and (6), a unitization order becomes effective on the date set out in the order, but that date shall not be less than 30 days after the day on which the order is made.

  • Marginal note:Order revoked

    (6) The Minister shall immediately revoke a unitization order that varies a unit agreement or a unit operating agreement if, before the effective date of that order, the applicant files with the Minister a notice withdrawing the application on behalf of the working interest owners or there are filed with the Minister statements objecting to the order and signed

    • (a) in the case of the unit agreement, by

      • (i) one or more working interest owners who own in total more than 25% of the total working interests in the unit area and are part of the group that owns 65% or more of the total working interests as described in subparagraph 48.22(3)(a)(i), and

      • (ii) one or more royalty owners who own in total more than 25% of the total royalty interests in the unit area and are part of the group that owns 65% or more of the total royalty interests as described in subparagraph 48.22(3)(a)(ii); or

    • (b) in the case of the unit operating agreement, by one or more working interest owners who own in total more than 25% of the total working interests in the unit area and are part of the group that owns 65% or more of the total working interests as described in subparagraph 48.22(3)(a)(i).

  • Marginal note:Application of sections 43 and 46

    (7) Sections 43 and 46 apply to the unitization order.

  • 2015, c. 4, s. 24
.

Marginal note:Amending unitization order

  •  (1) A unitization order may be amended on the application of a working interest owner submitted to both the Minister and the appropriate regulator.

  • Marginal note:Appointment of expert

    (2) The Minister and the regulator shall appoint an expert in accordance with subsections 48.27(2) to (4) for the purposes of this section.

  • Marginal note:Hearing

    (3) Once seized of the application, the expert shall hold a hearing at which all interested persons shall be given an opportunity to be heard.

  • Marginal note:Conclusion of hearing

    (4) On the conclusion of the hearing, the expert may request that the Minister order the amendment of the unitization order in accordance with the amendment proposed and to include in the order any variations to it that the expert determines are necessary to allow for the more efficient or more economical production of oil or gas from the unitized zone. If the expert makes such a request, the expert shall also request that the appropriate regulator order the amendment of its equivalent order in the same way.

  • Marginal note:Exception

    (5) If the expert finds that, on the day on which the hearing begins, one or more working interest owners who own in total 65% or more of the total working interests and one or more royalty interest owners who own in total 65% or more of the total royalty interests in the unit area have consented to the proposed amendment, the expert may end the hearing and request that the Minister amend the unitization order in accordance with the amendment proposed. If the expert makes such a request, the expert shall also request that the appropriate regulator amend its equivalent order in the same way.

  • Marginal note:Application of section 48.23

    (6) Section 48.23 applies, with any modifications that the circumstances require, to an amended unitization order.

  • 2015, c. 4, s. 24
.

Marginal note:Protection of tract participation ratios

 No amendment shall be made under section 48.24 that will alter the ratios between the tract participations of those tracts that were qualified for inclusion in the unit area before the commencement of the hearing, and, for the purposes of this section, the tract participations shall be those indicated in the unit agreement when it became subject to a unitization order.

  • 2015, c. 4, s. 24
.

Marginal note:Determination — percentages of interests

 The percentages of interests referred to in subsections 48.21(1), 48.22(3), 48.23(6) and 48.24(5) shall be determined in accordance with section 47.

  • 2015, c. 4, s. 24
.

Referral to Expert

Marginal note:Notice

  •  (1) The party that intends to refer a matter to an expert under subsection 5.1(9), 5.2(6), 48.14(2) or 48.18(2) shall notify the other party of their intention.

  • Marginal note:Appointment — single expert

    (2) Within 30 days after the day on which a notice is given under subsection (1) or an application is made under subsection 48.21(1) or 48.24(1), the parties shall agree on the appointment of an expert who shall be seized of the matter.

  • Marginal note:Appointment — expert panel

    (3) If the parties do not agree on the appointment of a single expert, they shall, within 30 days after the day on which the period to jointly appoint an expert under subsection (2) ends, each appoint one expert to a panel and those experts shall, in turn, jointly appoint an additional expert as chairperson. If there is no agreement on the appointment of a chairperson within 30 days after the day of the last appointment, the chairperson shall be appointed by the Chief Justice of the Federal Court within 30 days after the period for appointing a chairperson ends. Once the chairperson is appointed, the expert panel shall be seized of the matter.

  • Marginal note:Qualifications — expert

    (4) An expert shall be impartial and independent, and have knowledge or experience relative to the subject of disagreement between the parties.

  • Marginal note:Decisions

    (5) Decisions of an expert panel shall be made on the basis of a majority vote of the members. The chairperson’s vote is the deciding vote in the case of a tie.

  • Marginal note:Time limit

    (6) The expert’s decision shall be made no later than 270 days after the day on which they were seized of the matter.

  • Marginal note:Decision is final and binding

    (7) Subject to judicial review, a decision made by an expert is final and binding on all parties specified in the decision from the date specified in it.

  • Marginal note:Records to be kept

    (8) An expert shall cause records to be kept of their hearings and proceedings and shall deposit their records with the Minister when their activities to which the records relate have ceased.

  • 2015, c. 4, s. 24
.