Marginal note:Performance test reporting
22 (1) A responsible person for a boiler unit referred to in subsection 3(4) must send, to the Minister, a report containing the information referred to in Schedule 4 in relation to the performance test identified in section 5 no later than 60 days after the performance test was conducted.
Marginal note:Performance test verifier’s report — initial test
(2) In the case of a boiler unit referred to in subsection 3(4), the responsible person must obtain a report, signed by the performance test verifier, on the initial performance test, that contains the information referred to in Schedule 5 and send it to the Minister with their report referred to in subsection (1).
Version in force since January 1, 2019