Skip to content

Canadian Energy Regulator Act

S.C. 2019, c. 28, s. 10

In forceCurrent to September 30, 2026 History

Follow

Part 3 — Pipelines

Location of Pipelines

Section 198

Marginal note:Approval

 Except as otherwise provided in this Act, a company must not begin the construction of a section or part of a pipeline unless

  • (a) the Commission has issued a certificate in respect of the pipeline;

  • (b) the company has complied with all applicable conditions to which the certificate is subject;

  • (c) the plan, profile and book of reference of the section or part of the pipeline have been approved by the Commission; and

  • (d) copies, certified by the Regulator, of the approved plan, profile and book of reference have been deposited in the land registry office or other office where title to land is recorded for the area through which the section or part of the pipeline is to pass.

Version in force since August 28, 2019

Unofficial reproduction of the consolidated text published by the Department of Justice Canada, permitted by the Reproduction of Federal Law Order. Only the official text is authoritative.