Marginal note:Criteria
5 (1) These Regulations begin to apply in respect of a unit on the day on which the unit meets the following criteria and, subject to subsection 43(2), continue to apply until the responsible person for the unit submits the notice of permanent cessation of electricity generation in accordance with subsection 43(1):
Marginal note:Sum of electricity generation capacity
(2) Subject to subsection (3), a unit that has an electricity generation capacity of less than 25 MW is deemed to meet the criterion set out in paragraph (1)(a) if
Marginal note:Non-application — planned units
(3) These Regulations do not apply in respect of a planned unit that has an electricity generation capacity of less than 25 MW.