  •  (1) The Tribunal is not permitted to award the costs incurred by a complainant in preparing their response to a solicitation unless the response was compliant. The award shall not exceed 2% of the complainant’s bid price.

  • (2) If the Tribunal awards the costs incurred by the complainant in preparing their response to a solicitation, it is not permitted to also recommend that the complainant’s bid be re-evaluated, that a designated contract be awarded to the complainant or that the complainant be compensated.

  • (3) The Tribunal shall limit any recommendation of compensation under subsection 30.15(2) of the Act to one of the following:

    • (a) if the Tribunal determines that the designated contract should have been awarded to the complainant, the complainant’s lost profits on the designated contract, which shall not exceed 10% of the complainant’s bid price; and

    • (b) if it is not possible to determine whether the designated contract should have been awarded to the complainant, compensation for the lost opportunity to profit on the designated contract, which shall not exceed 10% of the bid price of the awarded contract divided by the number of potential suppliers for the designated contract.

  • (4) For the purposes of this section, the bid price for a designated contract does not include the value of any options or extensions of the designated contract.

  • SOR/2025-140, s. 11
.

Version in force since June 13, 2025

Unofficial reproduction of the consolidated text published by the Department of Justice Canada, permitted by the Reproduction of Federal Law Order. Only the official text is authoritative.