Section 2.1

 For the purposes of the Act, procurement process means the process that begins after a government institution has decided on its requirement and ends immediately after a designated contract is awarded. For greater certainty, it does not include the administration of an awarded designated contract, such as any actions taken or not taken by a government institution if it discovers after awarding the designated contract that the winning bid contained incorrect or incomplete information.