Part 4 — International and Interprovincial Power Lines

Location and Construction under Federal Law

Section 265

Marginal note:Prohibition

 A person must not begin the construction of a section or part of an international or interprovincial power line until

  • (a) the plan, profile and book of reference of the section or part are approved by the Commission; and

  • (b) copies, certified by the Regulator, of the approved plan, profile and book of reference have been deposited in the land registry office or other office where title to land is recorded for the area through which the section or part is to pass.

Version in force since August 28, 2019