Reduction of Carbon Dioxide Emissions from Coal-fired Generation of Electricity Regulations

SOR/2012-167

In forceCurrent to September 30, 2026 HistoryRegistered on August 30, 2012Made under: Canadian Environmental Protection Act, 1999

Follow

Part 1 — Regulated Units and Emission Limit

Emergency Circumstances

Section 7

Marginal note:Conditions for application

  •  (1) A responsible person for a unit may, under emergency circumstances described in subsection (2), apply to the Minister for an exemption from the application of subsection 3(1) in respect of the unit if the following conditions are satisfied:

    • (a) as a result of the emergency circumstances, there is a disruption, or a significant risk of disruption, to the electricity supply in the province where the unit is located; and

    • (b) the operation of the unit will end, decrease the risk of, or mitigate the consequences of, the disruption.

  • Marginal note:Criteria of emergency circumstances

    (2) An emergency circumstance is a circumstance

  • Marginal note:Application

    (3) The responsible person must, within 15 days after the emergency circumstance arises, provide the Minister with their application. The application must include the unit’s registration number, the date on which the emergency circumstance arose and information, with supporting documentation, to demonstrate that the conditions of paragraphs (1)(a) and (b) are satisfied.

  • Marginal note:Granting of exemption

    (4) The Minister must, within 30 days after receiving the application, grant the exemption if the Minister is satisfied that the conditions of paragraphs (1)(a) and (b) are satisfied.

  • Marginal note:Period of exemption

    (5) The exemption has effect as of the day on which the emergency circumstance arose and ceases to have effect on the earliest of

    • (a) the day that is 90 days after that day,

    • (b) the day specified by the Minister, and

    • (c) the earlier of

      • (i) the day on which the event referred to in paragraph (2)(a) ceases to cause a disruption, or a significant risk of disruption, to the electricity supply in the province where the unit is located, and

      • (ii) the day on which the measure, if any, referred to in paragraph (2)(b) ceases to be in effect.

Version in force since July 1, 2015

Unofficial reproduction of the consolidated text published by the Department of Justice Canada, permitted by the Reproduction of Federal Law Order. Only the official text is authoritative.