Reduction of Carbon Dioxide Emissions from Coal-fired Generation of Electricity Regulations

SOR/2012-167

In forceCurrent to September 30, 2026 HistoryRegistered on August 30, 2012Made under: Canadian Environmental Protection Act, 1999

Follow

Part 1 — Regulated Units and Emission Limit

Emergency Circumstances

Section 8

Marginal note:Extension

  •  (1) If paragraphs 7(1)(a) and (b) will continue to apply on and after the day on which an exemption granted under subsection 7(4) is to cease to have effect, the responsible person may, before that day, apply to the Minister for an extension of the exemption.

  • Marginal note:Application

    (2) The application must include the unit’s registration number and information, with supporting documentation, to demonstrate that

    • (a) paragraphs 7(1)(a) and (b) will continue to apply after the day on which the exemption is to cease to have effect; and

    • (b) steps — other than the operation of the unit during the period of the exemption — have been, and are being, taken to end, decrease the risk of, or mitigate the consequences of, the disruption.

  • Marginal note:Granting of extension

    (3) The Minister must, within 15 days after receiving the application, grant the extension if the Minister is satisfied that paragraphs (2)(a) and (b) have been demonstrated.

  • Marginal note:Duration

    (4) The extension ceases to have effect on the earliest of

    • (a) the day that is 90 days after the day on which the application for the extension was made,

    • (b) the day specified by the Minister, and

    • (c) the day referred to in paragraph 7(5)(c).

Version in force since July 1, 2015

Unofficial reproduction of the consolidated text published by the Department of Justice Canada, permitted by the Reproduction of Federal Law Order. Only the official text is authoritative.